Late April Update

  • Kitchens are now being installed and the scaffold has commenced coming down in some places.
  • Work is also being done to many of the bathrooms.
  • Tiling and the wooden floors are also being installed.

Settlement & Handover Process

It’s not been long since our last blog update … we have some exciting news to share with you.

Property Settlement Solutions (PSS) have been appointed to manage the settlement and handover process of your apartment.

PSS are a highly experienced team of property settlement professionals who will be contacting you very shortly to introduce themselves – after this time please direct any future queries that you may have relating to the settlement  of your apartment to the PSS team.

We will be updating the blog with some more photos in the coming weeks.

March Construction Update

Construction is still tracking ahead of schedule which is very exciting!

We’re anticipating that Settlement of the apartments could take place during the second half of July 2016.

Please note that this Settlement timeframe is an estimate / guide only, we will be providing a further update re this in the next few weeks.

We’ve added some new photos which will give you an indication of how it’s all progressing at Mayfield – please see below.
   
    
    
    
   

    

January Construction update

Building is progressing ahead of schedule.

All concrete works have been completed and the builder is working towards lockup.

We will be updating blog again shortly with more of a update and will be in touch during March with an estimated completion date.

   
    
    
  

October Construction Update

Construction work on Mayfield is proceeding well.

  • The basement and lower ground floor structure is complete
  • The ground floor slab nearing completion
  • You can see the view to the south west from the rear of level G (a fantastic view!)

 
  
 
      
  

September Construction Update

 

  • Construction is proceeding as planned.
  • Basement structure is almost complete.
  • Crane is adding panels to the building – the shape of the building will emerge quite quickly over the coming months.
  • An overview of the construction site can be seen by aircraft (taken in the last 4 weeks).

IMG_5106

IMG_5110

IMG_5108

IMG_5109

IMG_5105

IMG_5112

IMG_5002