October Construction Update Construction work on Mayfield is proceeding well. The basement and lower ground floor structure is complete The ground floor slab nearing completion You can see the view to the south west from the rear of level G (a fantastic view!)
September Construction Update Construction is proceeding as planned. Basement structure is almost complete. Crane is adding panels to the building – the shape of the building will emerge quite quickly over the coming months. An overview of the construction site can be seen by aircraft (taken in the last 4 weeks).